M. Veyvah Harbour Project 88% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has announced that the work on the design and build of M. Veyvah Harbour is well underway, with overall 88% project progress. The company has commenced harbor bridge beam concrete works on 28th June 2021.

The M. Veyvah Harbour project consists of; dredging and excavation operations of 66,831cbm; construction of a 350m breakwater; a 380m quay wall; a 130m revetment; installation of 1,880sqm of paved area and installation of streetlights.

- Advertisement -

According to MTCC, the value of the project is MVR 48.6 million.

- Advertisement -