Maldives Transport and Contracting Company (MTCC) has announced that it has completed the construction of breakwater of N. Miladhoo Harbor yesterday.
The construction of revetment is currently ongoing, with 56% completion. MTCC’s target is to complete the project before the end of this year.
The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment; a 286m quay wall; 1,430sqm of paved area; installation of navigation lights and streetlights.
According to MTCC, the value of the project is MVR 42.1 million.