Maldives Transport and Contracting Company (MTCC) has provided an update on the M. Muli Airport development project.
According to MTCC, the design and build of M. Muli Airport is currently underway. Runway reclamation and fire building plastering works are currently ongoing at the site, with 42% and 68% completion respectively.
Project works involve, reclamation operations of 14 hectares; coastal protection operations of 1,812m; construction of a 1200m x 30m runway; taxiway and an apron.
MTCC states that the value of the project is MVR 221.733 million.