MTCC Provides Update on Sh. Lhaimagu Harbour Development Project

Maldives Transport and Contracting Company (MTCC) has provided an update on the Sh. Lhaimagu Harbour Development Project.

According to MTCC, quay wall block installation works for Sh. Lhaimagu Harbour Development Project have been completed. Quay wall concrete works are currently ongoing at the site.

- Advertisement -

Sh. Lhaimagu Harbour project consists of dredging and excavation operations of 31,000cbm, construction of a 350m breakwater, a 276m quay wall, a 500m revetment, installation of 1,380sqm pavement, and installation of navigation lights and streetlights.

MTCC revealed that the value of the project is MVR 56.3 million.