MTCC Reports 76% Completion of HA. Muraidhoo Harbour Development Project

The Maldives Transport and Contracting Company (MTCC) has reported that the HA. Muraidhoo Harbour Development Project is currently at a 76% overall completion rate. 

The third shipment of rock boulders has been delivered to the project site, and breakwater profiling work has reached 90% completion. Dredging work for the new entrance channel has been completed.

- Advertisement -

The project includes dredging operations of 32,721 cubic metres for the new harbour basin and 3,817 cubic metres for the channel. It also involves the construction of a 232-metre quay wall, a 395-metre breakwater, a 202-metre revetment, 50-metre groynes, and the installation of 1,933 square metres of harbour pavement. Additionally, the project includes the construction of a ramp, a concrete bridge, and the installation of streetlights and navigational aids.

The total value of the project is MVR 37.69 million.