N. Miladhoo Harbor Development Project 59% Complete

Maldives Transport and Contracting Company (MTCC) has revealed that the work on design and build of N. Miladhoo Harbor Development Project is well underway, with overall 59% project progress.

MTCC has commenced the concrete works of the quay wall.

- Advertisement -

The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 209m breakwater; a 152m revetment; a 286m quay wall; 1,430sqm of paved area; installation of navigation lights and streetlights.

According to MTCC, the value of the project is MVR 45.26 million.