Quay Wall Concrete Works for Lh. Hinnavaru Harbour Extension Project Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has provided an update on the Lh. Hinnavaru Harbour Extension Project.

MTCC has completed quay wall concrete works for Lh. Hinnavaru Harbour Extension Project. Harbour pavement casting works are currently ongoing.

- Advertisement -

Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a 123.9m breakwater; a 170.55m revetment.

According to MTCC, the value of the project is MVR 99.52 million.