Sh. Foakaidhoo Harbor Development Project 62% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) states that the work on design and build of Sh. Foakaidhoo Harbor Development is well underway, with overall 62% project progress. 

According to MTCC, the fourth shipment of precast concrete blocks required for quay wall construction has been delivered to the project site on 15th April 2022. 

- Advertisement -

Project work consists of  dredging operations of 45,795cbm, construction of a 464m quay wall, a 100m revetment, a 507m breakwater, installation of 2320sqm harbor pavement, installation of streetlights and navigation lights.

The value of the project is MVR 64.6 million.