Sh. Foakaidhoo Harbor Project 41% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has revealed that the work on the design and build of Sh. Foakaidhoo Harbour is underway, with overall 41% project progress.

The second shipment of rock boulders required for the breakwater construction has been delivered to the project site.

- Advertisement -

The Sh. Foakiadhoo Harbour project consists of new harbor basin dredging operations of 39,995cbm; existing harbor basin dredging operations of 1800cbm; channel dredging operations of 4000cbm; construction of a 507m breakwater; a 100m revetment; a 464m quay wall; 2,320 sqm of paved area and installation of navigation lights and streetlights.

According to MTCC, the value of the project is MVR 52.7 million.

- Advertisement -