Maldives Transport and Contracting Company (MTCC) has completed dredging operations of new harbor basin of Sh. Feydhoo Harbor.
Following the dredging operations, the channel dredging operations are currently ongoing, with 66% completion.
The scope of the project includes, dredging operations of 27,500cbm, construction of a 276m quay wall, a 90m revetment, a 378m breakwater, installation of 1380sqm harbor pavement, installation of navigation lights and streetlights.
This project is valued at MVR 33.1 million.