Maldives Transport and Contracting Company (MTCC) has provided an update on the Adh. Hangnaameedhoo Harbour Development Project.
MTCC reveals that work on the design and build of Adh. Hangnaameedhoo Harbor Development Project is ongoing, with overall 77% project progress. The last shipment of precast concrete blocks required for quay wall construction have been delivered to the project site.
The scope of the project consists of; dredging and excavation operations of 6,363.1cbm; construction of a 204m breakwater; a 266m quay wall; a 160m revetment; installation of 1,330sqm of paved area and installation of streetlights.
According to MTCC, the value of the project is MVR 29.1 million.
- Advertisement -