CEO Adam Azim Inspects Progress of MTCC Projects in Ha. Hoarafushi and Ha. Ihavandhoo

CEO of Maldives Transport and Contracting Company (MTCC), Adam Azim has inspected the progress of Ha. Hoarafushi ferry terminal development project. Overall project progress is 63%.

He also inspected the progress of Ha. Hoarafushi coastal protection project. The scope of the work is laying a 280 meter geo bag revetment. Overall project progress is 13%.

- Advertisement -

Furthermore, he inspected the progress of Ha. Ihavandhoo ferry terminal development project. Overall project progress is 57%.

He also inspected the progress of Ha. Ihavandhoo Harbor Project. The scope of the project includes dredging 21295 cbm from harbor basin & construction of a 292m breakwater, 203m revetment, 509m quay wall, and pavement of 4582 sqm area. Overall project progress is 52%.

During the visits, the media was also briefed on the latest updates of the projects.