Construction of Internal Roads for Fuvahmulah 50% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has revealed that the construction of internal roads for Gn. Fuvahmulah is well underway, with overall 50% project progress. Installation of settlement tanks and electrical junction box are currently ongoing, with 71% and 70% completion respectively.

Scope of works for the project include sub base preparation of 122,659sqm; an asphalt wearing course of 95, 239 sqm; footpath preparation of 27,450sqm; road marking, streetlights, and storm water drainage works of 19,940m.

- Advertisement -

According to MTCC, the value of the project is MVR 271.3 million.