Dredging Operations of Dh. Hulhudheli Harbour 82% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has revealed that dredging operations of Dh. Hulhudheli Harbor is well underway, with overall 82% completion.

The first shipment of precast concrete blocks required for the construction of quay wall have been delivered to the project site on 23rd August 2021.

- Advertisement -

Scope of works for the project include dredging and excavation operations of 49,612 cbm; the construction of a 432m quay wall; a 337m breakwater; and a 252m revetment. Additionally, the installation of 1,645sqm of paved area and streetlights will also be undertaken.

According to MTCC, the value of the project is MVR 39.8 million.