Lh. Hinnavaru Harbour Development Project 66% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has provided an update on the Lh. Hinnavaru harbour development project.

MTCC revealed that work on the design and build of Lh. Hinnavaru harbour development project is well underway, with overall 66.48% project progress. The company has completed the construction of quay wall, breakwater and groyne.

- Advertisement -

Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a 123.9m breakwater; a 170.55m revetment.

According to MTCC, the value of the project is MVR 99.52 million.