B. Kamadhoo Harbor Development Project undertaken by Maldives Transport and Contracting Company (MTCC) has achieved a project completion rate of 78%.
The project has completed jetty construction work, and it recently received its fourth shipment of rock boulders for further development.
The project includes a series of tasks, such as 30,122 cubic metres of harbour dredging operations, 5,085 cubic metres of channel dredging operations, the construction of a 187-metre breakwater, a 656-metre revetment, a 402-metre quay wall, two concrete ramps, a scour apron, and an 80-metre by a 1.5-metre concrete jetty.
Additionally, it involves the installation of 1,810 square metres of harbour pavement, navigational and harbour lights, and mooring rings. The project is valued at MVR 51.4 million.