Maldives Transport and Contracting Company (MTCC) has provided an update on the L. Fonadhoo Road Construction Project.
According to MTCC, settlement tank installation work is currently ongoing under Phase 2 of the L. Fonadhoo Road Construction Project. Furthermore, MTCC has completed 93% of stormwater pipe installation work and 53% of sidewalk construction work.
The scope of the project works includes the construction of a 27,179 sqm carriageway, a 10,392 sqm pavement, installation of a stormwater management system, road markings, and streetlights.
The value of the project is MVR 53.9 million.