S. Hulhudhoo Harbour 63% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has stated that work on S. Hulhudhoo Harbour is well underway, with overall 63% project progress.

The company has now completed dredging operations of the new harbor basin.

- Advertisement -

The S. Hulhudhoo Harbour project consists of; dredging and excavation operations of 88,623cbm; construction of a 114m breakwater; a 624m revetment; a 742m quay wall; 2,250 sqm of paved area and installation of streetlights.

According to MTCC, the value of the project is MVR 65.1 million.