S. Hulhudhoo Harbour Project 68% Complete: MTCC

Maldives Transport and Contracting Company (MTCC) has revealed that work on design and build of S. Hulhudhoo Harbour is underway, with overall 68% project progress.

The installation of precast concrete blocks and concrete works required for the quay wall are currently ongoing at the project site.

- Advertisement -

The S. Hulhudhoo Harbour project consists of dredging and excavation operations of 88,623cbm; construction of a 114m breakwater; a 624m revetment; a 742m quay wall; 2,250 sqm of paved area and installation of streetlights.

According to MTCC, the value of the project is MVR 65.1 million.