S. Hulhudhoo Harbour Project Nears Completion

Maldives Transport and Contracting Company (MTCC) has revealed that the work on design and build of S. Hulhudhoo Harbor is well underway, with overall 81% project progress.

The construction of quay wall is currently ongoing as well, with 89% completion.

- Advertisement -

The S. Hulhudhoo Harbour project consists of; dredging and excavation operations of 88,623cbm; construction of a 114m breakwater; a 624m revetment; a 742m quay wall; 2,250 sqm of paved area and installation of streetlights.

According to MTCC, this project is valued at MVR 66.3 million.