Maldives Transport and Contracting Company (MTCC) has announced that the 2nd shipment of rock boulders required for breakwater construction of N. Miladhoo Harbor have been delivered to the project site on 24th April 2021.
The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment; a 286m quay wall; 1,430sqm of paved area; installation of navigation lights and streetlights.
According to MTCC, the value of the project is MVR 42.1 million.
- Advertisement -