Maldives Transport and Contracting Company (MTCC) has provided an update on the Ga. Dhaandhoo Harbour Development Project.
The second shipment of precast concrete blocks required for quay wall construction for Ga. Dhaandhoo Harbour Development Project, have been delivered to the project site.
Scope of the project works involve: 52,099cbm of harbor dredging operations, 4953cbm of channel dredging operations, construction of a 30m groyne, a 333m breakwater, a 170m revetment, a 529m quay wall, installation of 1203sqm of harbor pavement.
According to MTCC, the value of the project is MVR 70.8 million.